No |
Contract
Title |
Description |
Year |
Duration |
Location |
Contractor |
Asset
Owner |
Project
Type |
|
1 |
Bukit Tua Development – Corrosion Management Plan (CMP),
Corrosion Design Basis Memorandum (CDBM) |
To
develop and to review CMP, CDBM and material selection for Bukit Tua WHP, in-field flowline and
pipeline. |
2012 |
3 |
Indonesia |
PT
Ketapang II Ltd / Petronas |
Petronas |
Engineering
- PREFEED/FEED |
|
2 |
Besar
A -
CMP, CDBM and material selection |
To develop
CMP, CDBM and material selection for Besar A &
B satellite platforms, pipelines and onshore
receiving facilities. |
2012 |
3 |
Malaysia |
RNZ
Integrated |
Petronas |
Engineering
- PREFEED/FEED |
|
3 |
Block
A project |
To
perform corrosion risk assessment and material selection for topsides
equipment and piping. |
2013 |
1 |
Indonesia |
PT
Synergy Engineering |
PT
MEDCO E&P Malaka
|
Engineering
- PREFEED/FEED |
|
4 |
Revision
of ANDRA and ANPGA CDBM for ANGSI booster compressor upgrade |
To review
and to update the existing CDBM and CMP, gap analysis of the existing
facilities resulted by the new booster compressor upgrade on ANPGA. |
2013 |
2 |
Malaysia |
MMC
Oil & Gas |
Petronas |
|
|
5 |
Development
of CMP for Permas and Belum Pipelines |
To
develop CMP for MOC’s new Permas and Belum export
pipelines. |
2013 |
1.5 |
Malaysia |
Pegasus
APEC / Murphy Oil |
|
||
6 |
Development
of Integrity Management Plan for Santos Maleo MOPU |
To
develop overall asset integrity management plan (IMP) for the Mobile Offshore
Production Unit (MOPU) topside facilities. |
2013 |
2 |
Indonesia |
PT
Synergy Engineering |
Santos Maleo
|
|
|
7 |
Corrosion
and material studies for Premier Oil West Lobe Development |
To perform
corrosion impact studies and material selection for the in-field flowline,
West Lobe and AGX platforms. |
2013 |
2 |
Indonesia |
PT
Synergy Engineering |
Premier
Oil |
|
|
8 |
Seawater
Booster Pump Failure Analysis |
To
perform offshore in-service inspection and failure analysis of the seawater
booster pumps on the Cakerawala Platform. |
2013 |
1 |
Malaysia |
Intetech
Ltd |
CHOC |
Audit
& Inspection |
|
9 |
Pulai
A to Tinggi A Pipeline Replacement
Project |
To
develop CDBM & CMP for Pulai A to Tinggi A pipe-in-pipe reinforced
thermoplastic (RTP) pipeline Replacement Project. |
2013 |
2 |
Malaysia |
RNZ
Integrated |
Petronas |
|
|
10 |
Development
of CDBM for SBO Samarang Pipeline Replacement
Project |
To
develop CDBM & CMP for SBO Samarang pipeline
replacement project. |
2013 |
1 |
Malaysia |
RNZ
Integrated |
Petronas |
|
|
11 |
Development
of CDBM for Pre-FEED and FEED PFLNG Tie-in |
To develop
CDBM for PFLNG Tie-in facilities, brownfield modification and export
pipelines. |
2013 |
2 |
Malaysia |
MMC
Oil & Gas |
Petronas |
|
|
12 |
Study
of Duplex and Super Duplex Stainless Steels or Equivalent for High
Temperature Services |
To
evaluate suitability of Duplex and Super Duplex stainless steels or
equivalent materials for wet gas service above 150°C for Bunga Raya field
(BRE) Gas Improvement Project (GIP). |
2013 |
0.5 |
Malaysia |
MMC
Oil & Gas / Talisman |
|
||
13 |
Material
Selection for CPOC B17 Block Phase 3 Development Project |
To
perform corrosion studies and material selection report for CPOC B17 block
Phase-3 pipelines, topsides and brownfield
modification. |
2013 |
2 |
Malaysia-Thailand
JDA |
RNZ
Integrated / CPOC |
|
||
14 |
Bardegg
2
& Baronia EOR, Tukau Timur A & B – Material Selection, CDBM and CMP |
To
develop CDBM, CMP for various greenfield development and new pipelines. |
2013 |
5 |
Malaysia |
RNZ
Integrated |
Petronas |
|
|
15 |
Bardegg
2 & Baronia EOR, Tukau Timur A & B – Asset Integrity
assessment |
To
perform asset integrity assessment, gap analysis, remaining life analysis
investigation, API579 Fit-For-Service examination (Level 1 and 2) for
brownfield and impact studies resulted by the new development. |
2013 |
2 |
Malaysia |
RNZ
Integrated |
Petronas |
|
|
16 |
Diamond
Development Project EPCC CMP and RBI development |
To
develop CMP, asset register, database population, development of piping
loop/circuit and P-RBI for Diamond Development Project, PCVL. |
2013 |
5 |
Vietnam |
RNZ
Integrated / PCVL |
Engineering
- DDE/EPCC |
|
|
17 |
Diamond
Development Project EPCC UT Inspection |
To
perform baseline UTTG inspection for Diamond Development EPCC Project, PCVL. |
2013 |
5 |
Vietnam |
RNZ
Integrated / PCVL |
Audit
& Inspection |
|
|
18 |
CDBM of
the FEED for the TGAST-OSC-GPPA (TOG) Modification Project |
To
perform corrosion studies and to develop CDBM for the TGAST-OSC-GPPA (TOG)
modification project. |
2013 |
1.5 |
Malaysia |
MMC
Oil & Gas |
Petronas |
|
|
19 |
Corrosion
Studies and Material Selection for EPS-TPF Topside |
To
perform corrosion analysis and material selection for EPS-TPF topside. |
2013 |
1 |
Malaysia |
Gryphon
Energy |
|
||
20 |
Corrosion
Impact Studies for ANOA-FPSO Liquid Pipeline |
To
perform corrosion impact analysis for 8 inch liquid pipeline from ANOA to
PLEM, rigid riser at ANOA and flexible riser from PLEM to FPSO based upon
changed of production conditions. |
2013 |
0.5 |
Indonesia |
Premier
Oil |
|
||
21 |
Corrosion
Studies and Material Selection of FEED for KRA South Infill |
To
perform corrosion analysis and to propose material selection corrosion
mitigation measures for the new facilities on KRA-S platform. |
2013 |
0.5 |
Indonesia |
Star
Energy (KAKAP) Ltd |
|
||
22 |
Corrosion
Study And Material Selection For The Madura BD WHP
Topside Facilities |
To
perform corrosion analysis and to propose material selection corrosion
mitigation measures for the new Madura Straits Block BD WH platform. |
2013 |
1 |
Indonesia |
Husky-CNOOC
Madura Ltd |
|
||
23 |
Cendor
Gas Lift De-Bottlenecking Corrosion
Assessment |
To
perform asset integrity study, gap analysis and API579 Fit-For-Service
examination (Level 1 and 2) of the existing CDW-B gas lift system. |
2013 |
2 |
Malaysia |
Petrofac
Malaysia |
|
||
24 |
CO2
Corrosion Assessment and Material Selection Review for Cendor CO2 Removal Package |
To
assess the extent of CO2 corrosion expected in the CO2 removal package, to
identify the high corrosion risk areas and to propose corrective measures to
mitigate the corrosion threats to the carbon steel facilities. |
2013 |
1 |
Malaysia |
Sedia
Teguh / MMHE |
|
||
25 |
Expert
Witness for Molten Sulphur Tank Failure |
To perform
in-service inspection and to deliver expert evidence from the domain of
metallurgy and corrosion which led to the premature molten sulphur tank
failure. |
2013 |
2 |
Malaysia |
Undisclosed |
|
||
26 |
Corrosion
Study and Material Selection for Layang FPSO Topsides |
To
provide the corrosion assessment, to identify the optimal material selection
and to outlines general corrosion mitigation for the Layang FPSO topside facilities. |
2014 |
0.5 |
Malaysia |
Blackstone
Process Solutions / THHE / JX Nippon |
|
||
27 |
Critical
Review of Material Selection report for Kinabalu Field Re-development Project |
To
provide critical (third party) review of corrosion study and material
selection report of Kinabalu CPP and WHP. |
2014 |
0.5 |
Malaysia |
DRL Engineering
/ Talisman Malaysia |
|
||
28 |
Tungku
Gas
Plant NG Pipeline Corrosion Study and Material Selection – Feasibility and
Conceptual |
To
provide corrosion studies and material selection for the natural gas pipeline
project from Tungku Gas Plant to Puala Maura Besar. The pipeline
project also consist of the booster compressor
facility, condensate handling facility, gas conditioning facility, fire water
network. |
2014 |
0.5 |
Brunei |
Petrokon
Utama / Barakas Power Management Company |
|
||
29 |
Lengo
Facilities Study Corrosion and Material
Selection Study - Conceptual |
To
provide the corrosion assessment, to identify the material selection and to
outlines general corrosion mitigation for the Lengo field WHP topsides and export pipeline. |
2014 |
1 |
Indonesia |
Kris Energy |
|
||
30 |
Corrosion
Assessment and Material Selection for KG-D6 Onshore Terminal Booster
Compressor Station (OTBC) |
To
perform material selection and corrosion assessment of the new and existing
facilities impacted by the installation of OTBC. |
2014 |
1 |
India |
Aker Powergas / Reliance Industries |
|
||
31 |
Corrosion
Assessment Of The In-Service Pangkah
Gaslift and Multiphase Pipelines |
To
perform corrosion risk analysis, pipeline integrity assessment, to develop
detailed corrosion mitigation program of the HESS Pangkah
gaslift and multiphase pipelines. |
2014 |
1 |
Indonesia |
Hess
Indonesia |
|
||
32 |
Floating
Water Injection Feasibility Study Material Selection, CMP- Conceptual |
To perform
material selection and to develop corrosion management plan for the Water
Injection System to deliver 30,000 bbl/day on a
floating unit offshore. |
2014 |
2 |
Malaysia |
Overdick
/
Petronas |
Petronas |
|
|
33 |
SK310
B15 Topside and Export Pipeline Corrosion Study and Material Selection –
Conceptual |
To
perform corrosion analysis and material selection for the SK310 B15 platform
topside and export pipeline to B11. |
2014 |
1 |
Malaysia |
DRL
Engineering / SK Energy |
|
||
34 |
ANGSI
TCEOR (Terengganu Chemical EOR) CDBM – FEED |
To
perform corrosion analysis and material selection for the seawater intake
system, onshore seawater treatment plant (chlorinated/dechlorinated,
deaerated, chemical treatment) and the export systems. |
2014 |
3 |
Malaysia |
RNZ
Integrated |
Petronas |
|
|
35 |
ANGSI
TCEOR (Terengganu Chemical EOR) Asset Integrity Assessment (AIA) – FEED |
To
perform asset and pipeline integrity assessment, gap analysis, remaining life
investigation, API579 Fit-For-Service examination (Level 1 and 2) for
existing offshore facilities impacted by the new TCEOR program. |
2014 |
1 |
Malaysia |
RNZ
Integrated |
Petronas |
|
|
36 |
ANGSI-B
Revisit Project CDBM – Conceptual |
To
provide the corrosion assessment and material selection for the infill
drilling project on AnDP-B platform. |
2014 |
2 |
Malaysia |
RNZ
Integrated |
Petronas |
|
|
37 |
ANGSI-B
Revisit Project CMP, RBI development –
Conceptual |
To develop
asset database register and population, and development of piping
loop/circuit. |
2014 |
1 |
Malaysia |
RNZ
Integrated |
Petronas |
|
|
38 |
F-9
Infill Drilling Project CDBM – Detailed Design |
To
perform corrosion analysis and material selection for the F9JT-A infill
drilling project. |
2014 |
1 |
Malaysia |
RNZ
Integrated |
Petronas |
|
|
39 |
Bunga Pakma Topside, Tie-in Corrosion and Material, CMP –
FEED |
To
perform corrosion analysis, evaluation of corrosion mitigation measures (e.g.
material selection), and recommendation of the corrosion management plan for
the topsides facilities. |
2014 |
1 |
Malaysia |
MMC
Oil & Gas / Talisman Malaysia |
|
||
40 |
OSC
Modification Project CDBM – detailed design |
To
provide corrosion assessment and material selection, recommendation of the
corrosion management plan for the tie-in facilities. |
2014 |
2 |
Malaysia |
MMC
Oil & Gas |
Petronas |
|
|
41 |
OSC Modification
Project CMP + RBI + baseline UT survey – detailed design |
To
develop asset register, database population, development of piping
loop/circuit, in-situ baseline inspection for the OSC modification
facilities.
|
2014 |
3 |
Malaysia |
MMC
Oil & Gas |
Petronas |
|
|
42 |
North
Malay Basin Pipeline Internal Corrosion Study – Detailed Design |
To
review and update FEED corrosion study and to confirm material selection and
corrosion allowance for all the for 5 rigid subsea pipelines in North Malay
Basin.
|
2014 |
2 |
Malaysia |
RNZ
Integrated / HESS |
|
||
43 |
North
Malay Basin Pipeline CMP – Detailed Design |
To
develop CMP for 5 subsea pipelines in North Malay Basin.
|
2014 |
2 |
Malaysia |
RNZ
Integrated / HESS |
|
||
44 |
B15 topsides
and pipeline CDBM and CMP |
To
develop FEED CDBM and CMP for the B15 topside facilities and 80 km export
pipeline. |
2014 |
2 |
Malaysia |
RNZ
Integrated / SapuraKencana Energy |
|
||
45 |
BLOCK
SK 311 Wangsa Field Pipeline Project CDBM - FEED |
To
provide the corrosion rate assessment and material selection for the 8 inch
multiphase gas pipeline from WG-SA to SE-PA Platform. |
2014 |
1 |
Malaysia |
RNZ
Integrated / Murphy |
|
||
46 |
South Acis Field 10” Multiphase Gas Pipeline CMP – FEED |
To
outline corrosion monitoring, mitigation and inspection plans for the 10”
multiphase gas pipeline from SA-SA to SA-PA platform. |
2014 |
1 |
Malaysia |
RNZ
Integrated / Murphy |
|
||
47 |
Bardegg
2 & Baronia EOR, Phase 2 – Brownfield CDBM and asset integrity studies |
To
develop CDBM, CMP for various tie-in piping and pipelines; to perform impact
studies and asset integrity studies for brownfield.
|
2014 |
2.5 |
Malaysia |
RNZ
Integrated |
Petronas |
|
|
48 |
Corrosion
study and material selection for Bangka Topside facilities |
To
perform the corrosion rate assessment and material selection for the Bangka
topside facilities. |
2014 |
1 |
Indonesia |
Meindo
/
Chevron |
|
||
49 |
CDBM
for Dalak Gas receiving facilities |
To
provide the corrosion assessment and material selection for the new onshore
gas receiving facilities. |
2014 |
2 |
Malaysia |
Toyo
Engineering |
Petronas |
|
|
50 |
CMP for Dalak Gas
receiving facilities |
To develop
asset database register and population, and development of piping
loop/circuit. |
2014 |
2 |
Malaysia |
Toyo
Engineering |
Petronas |
|
|
51 |
Kasawari
field development – CDBM,
asset integrity study |
To
develop CDBM for greenfield and tie-in piping and pipelines; to perform
impact studies and asset integrity studies for brownfield.
|
2014 |
1.5 |
Malaysia |
RNZ
Integrated |
Petronas |
|
|
52 |
Magtymguly
gas recycling development – CDBM |
To
develop CDBM for 5 greenfield and brownfield platforms for the Magtymguly gas
recycling project. |
2014 |
2 |
Turkmenistan |
RNZ
Integrated / Petronas Turkmenistan |
|
||
53 |
PMO
Pipeline rehabilitation project – internal and external corrosion studies |
To perform
internal and external corrosion assessment for two aging pipelines, as part
of the pipeline rehabilitation project. |
2014 |
1 |
Malaysia |
MMC
Oil & Gas / Petronas |
Petronas |
Specialist
Corrosion Study |
|
54 |
Angsi
Water Flood Optimisation (WFO) project – CDBM and asset integrity study. |
To
develop CDBM for water injection platform and to perform impact studies and
asset integrity studies for impacted brownfield.
|
2014 |
1.5 |
Malaysia |
RNZ
Integrated |
Petronas |
|
|
55 |
Material
of construction review for (4) new infill wells of Berantai Phase 2a WHP |
To
review the material selection the flowlines connecting the four (4) new
infill wells (BR-C1-B, BR-C1-C, BR-C2-A and A08-ST) and the tie-in header
with respect to carbon steel and duplex stainless steel. |
2014 |
1 |
Malaysia |
RNZ
Integrated / Petrofac |
|
||
56 |
B4
and B6 MOAB FEED Study – Corrosion study and Material Selection |
To
perform corrosion study and material selection for the topside facilities of
the B4 and B6 MOAB platforms. |
2014 |
2 |
Baltic
Sea |
Overdick
/ CalEnergy Resources |
|
||
57 |
Bardegg
2 & Baronia EOR, Detailed Design Package 3 – Brownfield CDBM |
To perform
FEED verification, review and update DD CDBM various tie-in piping and
pipelines.
|
2015 |
2 |
Malaysia |
RNZ
Integrated |
Petronas |
|
|
58 |
Bardegg
2
& Baronia EOR, Detailed Design Package 2 –
TTJT-A and BNJT-K CDBM |
To
perform FEED verification, review and update DD CDBM for BNJT-K and TTJT-A
platforms.
|
2015 |
2 |
Malaysia |
Sapura Kencana Engineering / Petronas |
Petronas |
|
|
59 |
Melor
topside modification CMP And LCC
analysis |
To
develop corrosion management plan and to perform life cycle cost (LCC)
analysis for the melor topside piping replacement. |
2015 |
2 |
Malaysia |
MMCOG
Engineering / Petronas |
Petronas |
|
|
60 |
Thai Binh Field Development Project – CDBM, CMP and RBI |
To update
DD CDBM and CMP, to develop Post-AFC asset register, database population,
development of piping loop/circuit, baseline inspection and P-RBI for Thai Binh Field Development Project, PCVL. |
2015 |
5 |
Vietnam |
PVE /
PCVL |
|
||
61 |
Corrosion
impact assessment and material study for PM 304 gas utilisation project for
WD MOPU to FPSO pipeline |
To
perform Conceptual and feasibility study, including corrosion and material
impact studies for the gas utilisation project, to utilise the WD MOPU to
FPSO pipeline to transport excess gas for re-injection. |
2015 |
1 |
Malaysia |
Overdick
/ Petrofac |
|
||
62 |
Layang
& HIP Material selection study and Corrosion Management Plan (CMP) |
To perform
corrosion analysis and material selection for the Layang WHP and HIP modification project; subsequently to develop corrosion
management plan (CMP) for the said facilities. |
2015 |
2 |
Malaysia |
Sapura Kencana Engineering / NOEX |
|
||
63 |
Ghana
OCTP FPSO corrosion and material selection study |
To
perform corrosion assessment and material selection for the OCTP offshore
FPSO topside facilities. |
2015 |
2 |
Vietnam |
PTSC |
|
||
64 |
NMB
FSO topside conversion |
To perform
corrosion assessment and material selection for the NMB FSO topside
conversion facilities. |
2015 |
1.5 |
Malaysia |
Armada
TCPE / HESS |
|
||
65 |
Lengo
WHP, export pipeline and ORF Corrosion
Study and Material Selection - FEED |
To
revisit corrosion assessment, and to identify the material selection for the Lengo field WHP topsides, export pipeline and onshore
receiving facilities. |
2015 |
1.5 |
Indonesia |
Kris
Energy |
|
||
66 |
Bardegg
2
& Baronia EOR, Detailed Design Package 2 –CMP |
To
develop CMP for BNJT-K and TTJT-A platforms.
|
2015 |
2 |
Malaysia |
Sapura Kencana Engineering / Petronas |
Petronas |
|
|
67 |
Corrosion
assessment and material study for PM 304 gas utilisation project for WD MOPU
to FPSO pipeline |
To perform
FEED corrosion and material impact studies for the gas utilisation project,
to utilise the WD MOPU to FPSO pipeline to transport excess gas for
re-injection. |
2015 |
1 |
Malaysia |
Overdick
/ Petrofac |
|
||
68 |
Corrosion
study and material selection for FEED Bokor (CPP and Tie-in) phase 3 EOR
project |
To
perform FEED corrosion study and material selection of new BOKOR CPP and
tie-in facilities, for the phase 3 EOR project. |
2015 |
2 |
Malaysia |
MMCOG
Engineering / Petronas |
Petronas |
|
|
69 |
Corrosion
study and material selection for FEED Bokor WHPs phase 3 EOR project |
To
perform FEED corrosion study and material selection of new BOKOR WHPs topside
facilities, for the phase 3 EOR project. |
2015 |
2 |
Malaysia |
MMCOG
Engineering / Petronas |
Petronas |
|
|
70 |
Material, Corrosion and Inspection (MCI) engineering for Baronia Rejuvenation project |
To
provide MCI supports for Baronia Rejuvenation
project consists of 14 platforms. Tasks including identification of piping
replacement, impact assessment, remaining life analysis; and developing of
CDBM, CMP and RBI for the required facilities. |
2015 |
4 |
Malaysia |
RNZ
Integrated |
Petronas |
|
|
71 |
Materials
& Corrosion study for Alur Rambong (AR)
production facilities |
To perform
corrosion analysis and to evaluate feasibility of selecting carbon steel as
material of construction, for AR production facilities, including export
trunkline. |
2016 |
1 |
Indonesia |
MEDCO
Energy |
|
||
72 |
Assessment
of PMI and Ferrite test requirement for Alur Siwah (AS) CPP facilities |
To
perform risk assessment on the AS CPP facilities, subsequent to the probable
absence of PMI and Ferrite tests on CRA materials. |
2016 |
2 |
Indonesia |
MEDCO
Energy |
|
||
73 |
Internal
corrosion Prevention, Mitigation and
Material Selection for the New 30” 144 km Salman Sirri Subsea Gas Pipeline FEED Project |
To
perform corrosion analysis, recommend corrosion mitigation measure and to propose
material of construction for the pipeline FEED. |
2016 |
1 |
Iran |
Nautic
AWT / Iranian Offshore Oil Company |
|
||
74 |
Existing
30” 144 km abandoned Salman-Sirri Subsea Gas
Pipeline Corrosion and Integrity Assessment |
To
assess the historical corrosion monitoring/ inspection data, coupled with FFS
analysis and future corrosion modelling – to contribute to the overall
pipeline integrity assessment, to decide if the existing pipeline is safe to
further operate. |
2016 |
3 |
Iran |
Nautic
AWT
/ Iranian Offshore Oil Company |
|
||
75 |
Corrosion
and material studies for Premier Oil LAMA and West Lobe Development |
To
perform material selection for West Lobe infill wells and corrosion impact
studies for flowline, pipeline and process
facilities. |
2016 |
2 |
Indonesia |
Premier
Oil |
|
||
76 |
Dulang
Heat
Management and Corrosion Under Insulation (CUI) Study |
To
perform heat management, corrosion and RBI analysis
in order to identify CUI-prone areas, to eliminate insulation wherever
possible and mitigate CUI for Dulang platforms. |
2016 |
2 |
Malaysia |
Overdick
/
Petronas |
Petronas |
|
|
77 |
Bokor-Betty
Rejuvenation DED - CDBM |
To
develop CDBM for Bokor and Betty rejuvenation for topsides, downholes and pipelines detailed engineering design. |
2016 |
2.5 |
Malaysia |
MMCOG
/ Petronas |
Petronas |
|
|
78 |
Block
A Gas development flowlines, trunklines and
pipelines (FTP) EPC supports |
To
support Owner in Materials and Corrosion for Block A gas development FTP
project EPC. |
2016 |
1 |
Indonesia |
MEDCO
E & P |
|
||
79 |
LWP
to HIP jumper hose mode – materials and corrosion studies |
To
develop corrosion analysis and material selection for Layang WHP and HIP CPP jumper hose mode. |
2016 |
2 |
Malaysia |
Sapura Kencana / NOEX |
|
||
80 |
Sao Vang
Dai Nguyet Project – Pipeline material selection reports |
To
lead PVE Consultancy MCI Team in developing material selection for pipelines. |
2016 |
1 |
Vietnam |
PVEC
/ Idemitsu
|
|
||
81 |
Corrosion
analysis and pigging studies for Belida and North
Belut pipelines |
To
perform corrosion and material integrity studies to support client in
establishing pipeline pigging philosophy. |
2016 |
1 |
Indonesia |
ConocoPhilips
|
|
||
82 |
SO2
scrubber integrity study and material selection for Ujung Pangkah development onshore processing facilities |
To
perform failure analysis, integrity study of the premature damaged SO2
scrubber (OT > 800°C); to perform material selection exercise for the new
scrubber replacement. |
2016 |
3 |
Indonesia |
SAKA Energi
|
Specialist
Corrosion Study |
|
|
83 |
Topside
Material Selection Report and Corrosion Management Plan |
To
provide critical review of the Topside Material Selection Report and
Corrosion Management Plan for the Pegaga field
development project. |
2016 |
1 |
Malaysia |
Mubadala
Petroleum |
|
||
84 |
Bokor
CPP EPCC |
Lead
material and corrosion engineer of the EPCC team, to support overall material
and corrosion tasks and to develop DDE BOCPP CDBM. |
2017 |
5 |
Malaysia |
MMC-MMHE
/ Petronas |
Petronas |
Engineering
- DDE/EPCC |
|
85 |
Bardegg
package 3, P-RBI and CMP support |
To
develop CMP and to support for development of P-RBI for the Bardegg Package-3 facilities. |
2017 |
4 |
Malaysia |
RNZ
Integrated |
Petronas |
|
|
86 |
Besar
exhaust material study |
To
perform impact assessment of SS310S material as the GEG and DEG exhaust
piping. Specifically looking at the T-T-Sensitisation correlation and loss of
strength in the specified temperature regime. |
2017 |
1 |
Malaysia |
RNZ
Integrated |
Petronas |
|
|
87 |
Garagol
Deniz extension |
To provide
corrosion assessment and material selection for the new process scheme of Garagol Deniz West Drilling Platform A. |
2017 |
2 |
Turkmenistan |
RNZ /
Petronas (T) |
|
||
88 |
Conceptual
engineering for Baram Integrated Re-development
project |
To
provide materials and corrosion studies, asset integrity assessment, P-RBI
examination, and to support the decision to repair/replace for rejuvenation
and redevelopment of Baram field.
|
2017 |
4 |
Malaysia |
MMC /
Petronas |
Petronas |
|
|
89 |
FEED
for Bayan gas development project phase 2 |
To
develop CDBM for Bayan Topsides and export pipelines, and to perform P-RBI
examination on HTI pipeworks. |
2017 |
3 |
Malaysia |
MMC /
Petronas |
Petronas |
|
|
90 |
Bakong
, Larak, Gorek development
project |
To establish
CDBM, CMP and CMF for the Bakong
Larak, Gorek and BIM
(Brownfield Integrated Module). |
2018 |
3 |
Malaysia |
RNZ /
SEB, Shell |
|
||
91 |
Limbayong
Conceptual Engineering
Design |
To
develop CDBM for Limbayong Deepwater development
project, the scopes include SURF (Subsea, Umbilical, Flowline, Riser), the
FPSO topside and the HTI at Kinabalu. |
2018 |
3 |
Malaysia |
RNZ
Integrated |
Petronas |
|
|
92 |
PM304
– East Cendor Phase 1 Development Project |
To develop
material selection and CMF for topside and export pipelines for East Cendor Phase 1 Development Project. |
2018 |
2 |
Malaysia |
RNZ /
Petrofac Malaysia |
|
||
93 |
Engineering
and Detailed Design For D35 Simultaneous Production
& Drilling (SIPROD) |
To
develop CDBM and CMP to support for DDE of D35 SIPROD project, scope includes
D35DP-B, D35DP-A and D35JT-C platforms. |
2018 |
4 |
Malaysia |
RNZ /
ROC Oil |
|
||
94 |
PM9
Simplification project |
To develop
CDBM and asset integrity impact studies for the PM9 simplification project
involving Bekok-A, B, C and Tiong A platforms and
the interfiled pipelines. |
2018 |
2 |
Malaysia |
RNZ
Integrated |
Petronas |
|
|
95 |
EPCC
of Pegaga WHD and ICPP |
To
develop CDBM, CMP, RBI and to support EPCC for Pegaga WHD and ICPP topside development project.
|
2018 |
9 |
Malaysia |
PRW /
MDC |
|
||
96 |
FEED
for Dulang
A Infill
Project Kumang West Development Project |
To develop
CDBM and preliminary asset integrity study for the Dulang
A Infill Project Kumang West Development Project. |
2018 |
9 |
Malaysia |
PRW /
Petronas |
Petronas |
|
|
97 |
EPCC
of D18 Phase 2 and D28 Phase 1 project |
To
develop CDBM and to support EPCC for D18, D28 EPCC. |
2018 |
2 |
Malaysia |
MMC /
Petronas |
Petronas |
|
|
98 |
DDE
for HESS NMB Phase 2 development project |
To
develop material selection report for Anggerik, Zetung WHPs, intrafield pipeline and HTI at Kusumba. |
2018 |
4 |
Malaysia |
RNZ,
SEB / Hess |
|
||
99 |
Detailed
Design Competition Of Mobile Offshore Production
Unit (MOPU) For K5 Strategic Technology Project (STP) |
To
develop CDBM for the K5 MOPU topside and pipelines, DRCF and TTP. |
2018 |
4 |
Malaysia |
RNZ,
SEB / Petronas |
Petronas |
|
|
100 |
MEPA
Deep high CO2 NAG well feasibility study |
To
perform corrosion and material selection studies and integrity study for the
MEPA Deep high CO2 NAG well feasibility study project. |
2018 |
2 |
Malaysia |
MMC /
MOC |
|
||
101 |
DDE
for Beryl Development |
To develop
CDBM for the infill drilling Beryl wells and impact studies for the existing
HIP facilities. |
2018 |
3 |
Malaysia |
MMC /
JX NIPPON OIL & GAS EXPLORATION |
|
||
102 |
EPCC
of Pegaga export Pipeline and Tie-in |
To
develop material selection and CMP for Pegaga 38”
PL-395 export pipeline.
|
2018 |
3 |
Malaysia |
Synergy,
Pegasus / MDC |
|
||
103 |
Tembikai
OWF Project |
To
develop CDBM for Tembikai OWF WHP topside. |
2018 |
2 |
Malaysia |
Synergy
/ Vestigo
|
|
||
104 |
FEED
for Pemanis (PESA) - CDBM |
To develop
CDBM for the PESA platform, export pipeline from PESA to MEPA and hist-tie-in
at MEPA. |
2019 |
3 |
Malaysia |
MMC /
MOC |
|
||
105 |
Salman
Development Project |
To
develop CDBM for topside facilities, water injection and export oil
pipelines. |
2019 |
5 |
Brunei |
Sapura
Fabrication (SFSB)/ Brunei Shell |
|
||
106 |
SK408W Jerun Field Development Project |
To
develop CDBM and CMP for JRN-A and JRN-K topside facilities and export
pipeline. |
2019 |
2 |
Malaysia |
RNZ/ SapuraOMV Upstream (Sarawak) |
|
||
107 |
EPCC
for Heavy Oil Transportation System 2 (HOTS2) |
To
develop CMP, RBI study, and pipeline integrity management system for the
onshore HOTS2 pipeline and connecting facilities. |
2019 |
2 |
Iraq |
Dar
Energy/ Petronas Carigali Iraq Holding |
|
||
108 |
EPCC of
Oil Gathering Facilities Phase 4 (OGF4) |
To
develop CMP and RBI study for the new wellpads and
trunklines on OGF. |
2019 |
2 |
Iraq |
Dar
Energy/ Petronas Carigali Iraq Holding |
|
||
109 |
EPCC
of Water Management System (Phase 1) |
To
develop CMP, RBI study and the Condition Monitor Location for the waste water management facilities. |
2019 |
3 |
Iraq |
Dar
Energy/ Petronas Carigali Iraq Holding |
|
||
110 |
Pre-FEED
design for HI Development Project Nigeria |
To develop
material selection and corrosion management study for topside facilities. |
2019 |
1 |
Nigeria |
Dar
Energy/ Shell Petroleum |
|
||
111 |
Basic
Engineering Design for Effluent Management at Source (EMAS) Project |
To
perform corrosion assessment and material selection studies for EMAS project. |
2019 |
3 |
Malaysia |
MIE/
MRCSB |
|
||
112 |
M1
Produced Water Treatment (PWT) Upgrade Project |
To
develop CDBM for new M1 PWT system. |
2019 |
2 |
Malaysia |
MIE/
Petronas |
Petronas |
|
|
113 |
Provision
Engineering Services for Sand Technology Pilot Implementation at Baram Field |
To
develop CDBM for the new sand management facilities in Baram South. |
2019 |
1 |
Malaysia |
MIE/
Petronas |
Petronas |
|
|
114 |
Detail
Engineering Design Services for Tukau Appraisal
Project |
To
develop the Material Selection Report for the flowlines and gaslift injection lines on TKJT-E platform. |
2019 |
1 |
Malaysia |
Dar
Energy/ Petronas |
Petronas |
|
|
115 |
EPCIC
for Yetagun Acid Gas Removal Unit (AGRU) Project |
To develop
CDBM for AGRU package, the modification and tie-ins
due to installation of AGRU. Material selection of alloyed Titanium for
elevated temperature (c.a. 230’C), oxygenated and chlorinated seawater. |
2019 |
2 |
Myanmar |
MMC/SLB/PC
Myanmar (Hong Kong) Limited |
|
||
116 |
RBI
assessment and piping circuitization for Asean Bintulu Fertilizer (ABF) |
To
assist to establish the RBI study and inspection plan for the existing Urea,
Ammonia and Utility plants which have been operated for decades without
inspection. |
2019 |
14 |
Malaysia |
ABF |
|
||
117 |
Bid
support for Marjan Field Development |
To
verify the recommended material of construction, and to suggest material optimization
and upgrade to suit the corrosion needs of the facilities. |
2019 |
1 |
Saudi
Arabia |
Sapura/
Saudi Arabian Oil Company |
|
||
118 |
Umbrella
Contract Engineering Services for Facilities Improvement Proposal (FIP) &
Plant Change for Petronas |
To
develop CDBM for the new FWS pipeline (PL431) and gas lift pipeline (PL436). |
2019 |
2 |
Malaysia |
MIE /
Petronas |
Petronas |
|
|
119 |
Corrosion
Impact Study on Cargo Oil Tanks |
To perform
corrosion assessment and recommend mitigation measures for the COT3 tanks on
FPSO Kikeh. |
2019 |
2 |
Malaysia |
MDPC |
MDPC |
Specialist
Corrosion Study |
|
120 |
EPCI
of WHP PM304 – East Cendor Phase 1 Development
Project |
To
develop DDE CDBM for new process and utilities systems at East Cendor platform. |
2019 |
2 |
Malaysia |
Petrofac
Malaysia |
|
||
121 |
Provision
of Engineering for PC MTBE Flare Improvement Project |
To
develop corrosion assessment and material selection for new facilities under
the Flare Improvement Project at PC MTBE. |
2019 |
1 |
Malaysia |
RNZ
Integrated |
Petronas |
|
|
122 |
Provision
of Feasibility Study and Front End Engineering Design (FEED) Services for Kasawari E11R-A Host Tie-In Project |
To develop
corrosion assessment and material selection for new E11R-AA pipe to E11R-A
gas production header on Kasawari Field. |
2019 |
2 |
Malaysia |
MMC
Oil & Gas/ Petronas |
Petronas |
|
|
123 |
Provision
of Basic & Detailed Engineering, Procurement, Construction and
Commissioning (BEPCC) for ABF Third Boiler Project |
To
perform corrosion assessment and material selection studies for the new
tie-in and modification works for ABF third boiler project. |
2019 |
1 |
Malaysia |
Petrofac
RNZ |
ABF |
|
|
124 |
Provision
FEED studies for North Sisi Nubi Project |
To
review corrosion study and material selection report developed by Synergy. |
2019 |
1 |
East
Kalimantan, Indonesia |
Synergy
Indonesia / Pertamina
|
|
||
125 |
Provision
of Feasibility Study Service for Betty Redevelopment Project |
To
predict the extent of the corrosion rate that would occur on the carbon steel
and to justify the use of carbon steel with 3 mm CA for the BEDP-A water
injection pipeline. |
2018 |
2 |
Miri,
Malaysia |
MMC /
PCSB |
Petronas |
|
|
126 |
Provision
of Engineering Service for KAKG-A UB600 Project Corrosion Design Basis
Memorandum (CDBM), Asset Integrity Study |
To develop
corrosion assessment and material selection for the new tie-in facilities and
asset integrity studies for existing facilities. |
2020 |
4 |
Bintulu,
Malaysia |
MMC /
PCSB |
Petronas |
|
|
127 |
Provision
of EPCM for 2011 Baram Delta EOR Development
Project |
To
develop corrosion assessment and material selection for the new tie-in
facilities. |
2020 |
2 |
Miri,
Malaysia |
MMC /
PCSB |
Petronas |
|
|
128 |
Crude
Oil Tank Corrosion Assessment |
To
develop corrosion assessment for the Crude Oil Tank 3 on FPSO Kikeh.
|
2020 |
2 |
Sabah,
Malaysia |
MDPC |
|
||
129 |
Gasket
material study |
To
recommend and advise on the gasket material for the subsea pipeline. |
2020 |
1 |
Sarawak,
Malaysia |
Peritus
/ Mubadala |
|
||
130 |
Provision
of EPCC of Wellhead Platform for BKD-A and Host Tie-In Modification Project |
To
develop corrosion assessment and material selection for the new WHP and
tie-in on BNCPP-B. |
2020 |
2 |
Miri,
Malaysia |
2H
Offshore / PCSB |
Petronas |
|
|
131 |
Provision
of EPCIC for Bekok Oil Project |
To establish
risk-based inspection study for the 2 new wellhead platform and to recommend
condition monitoring locations for the new facilities. |
2020 |
3 |
Kerteh
, Malaysia |
Synergy
/ PCSB |
Petronas |
|
|
132 |
Pre-FEED
Design Competition for SPDC & JV-HA Development Project Nigeria |
To
recommend the initial material selection and corrosion management strategy,
cathodic protection philosophy, chemical injection requirements and external
coating and field joint coating selection philosophy. |
2020 |
1 |
Nigeria |
DAR
Energy / Shell |
|
||
133 |
Provision
of FEED for Mercury Removal Permanent Skid on MDPP and FSO |
To
provide recommendation of construction materials for the newly installed
mercury removal skids and connecting piping. |
2020 |
1 |
Gulf
of Thai |
Petrofac
RNZ / CPOC |
|
||
134 |
Deep Well
Infill Flowline Tie-in BRG-D6 Facilities Material Selection and Feasibility
Study |
To
develop corrosion assessment and material selection for the new deep well
production flowlines. Feasibility study is performed on the existing topside
facilities and intra-field pipeline to ensure the integrity due to fluids
commingling from the new deep well. |
2020 |
1 |
Gulf
of Thai |
Petrofac
RNZ / HESS |
|
||
135 |
Provision
of Engineering Services for Petronas Carigali Turkmenistan Project Feasibility Study at Area 36 & 38 |
To
perform material adequacy study at GTPOGT Areas 36 & 38 constructed with
non-sour service materials with presence of H2S, and to develop the corrosion
management plan for the facilities. |
2020 |
2 |
Turkmenistan |
DAR
Energy / PC(T)SB |
|
||
136 |
Provision
of FEED Services for Design One Build Many (D1BM) Project |
To
provide corrosion assessment and material selection recommendation for
topside piping and equipment of process and utility systems for base case
design and several sensitivity studies. |
2020 |
2 |
Malaysia |
Aker
Solutions / Petronas |
Petronas |
|
|
137 |
Entinde
FEED WHP and GPP |
To
develop corrosion assessment, recommendation of material selection and
corrosion monitoring philosophy for new IM WHP and onshore GPP facilities. |
2020 |
3 |
Limbe,
Cameroon |
Technip
FMC / New Age Cameroon Offshore Petroleum S.A. |
|
||
138 |
Provision
of Engineering Works For GOP-B Booster Compressor |
To
provide corrosion assessment and material selection for the new facilities on
GOP-B, including sand handling and booster compressor systems. |
2020 |
3 |
Malaysia |
MMC
Oil & Gas |
PTTEP |
|
|
139 |
Provision
of Pre-FEED Services for SK410B Lang Lebah Development |
To
provide corrosion assessment and recommendation of material selection for
Lang Lebah offshore facilities and export
pipelines. |
2020 |
2 |
Bintulu,
Malaysia |
Technip
FMC / PTTEP |
PTTEP |
|
|
140 |
Provision
of EPCIC of PM309 Gas Ledang
Redev Segment 2 Development Project |
To develop
corrosion assessment and material selection for the subsea production system,
subsea flowlines and new wellhead platform. |
2020 |
2 |
Terengganu,
Malaysia |
DAR
Energy |
Petronas |
|
|
141 |
EPCIC
for Salman Project |
To
develop Material & Corrosion Design Basis Report, Corrosion Management
Manual (CMM) and Corrosion Management Framework (CMF) for the wellhead
platform, water injection pipeline, umbilical and HP oil pipeline. |
2020 |
3 |
Brunei |
Petrokon
/ Brunei Shell |
|
||
142 |
Conceptual
Design (FEED) for SK318 TIMI Development |
To
develop FEED material selection and CMF for the host tie-in facilities of the
new Brownfield Integrated Module (BIM) and export pipeline. |
2020 |
2 |
Malaysia |
Petrokon
/ SSB |
|
||
143 |
Provision
of Leasing, Operating & Maintenance of Mobile Offshore Production Unit
(MOPU) for Bayan Redevelopment Project Gas Phase 2 |
To
develop corrosion assessment and material selection for BYG-AA facilities. |
2020 |
1 |
Bintulu,
Malaysia |
Tanjung
Offshore Services / Petronas |
Petronas |
|
|
144 |
Provision
of Engineering Services for Gansar PM6/12 Project |
To
develop asset integrity impact studies for the existing topside facilities
affected by new Gansar tie-in on the Duyong CPP. |
2020 |
2 |
Malaysia |
Aker
Solutions/ PCSB |
Petronas |
|
|
145 |
SK310
B14 Field Development Project |
To
provide preliminary corrosion assessment, material selection and corrosion
management plan for topside facilities on the B14 CPP and export pipeline |
2020 |
3 |
Malaysia |
Technip
FMC/ SapuraOMV
|
|
||
146 |
Provision
of Basic Engineering Study Services for Dulang
Redev 3.0 |
To
develop CDBM and asset integrity impact studies for the Dulang
Redev 3.0 project involving Dulang-D
platform and PMO PL16 crude oil pipeline.
|
2020 |
2 |
Malaysia |
DAR
Energy |
Petronas |
|
|
147 |
2020 |
1.5 |
Malaysia |
PT Synergy
Engineering |
Genting
Oil |
|
|||
148 |
2020 |
0.5 |
Brunei |
Mach3
Engineering |
Brunei
Shell |
|
|||
149 |
Material
selection for SEAQuestor Pilot Plant - DDE |
To provide
corrosion assessment and material selection for SEAQuestor Pilot Plant project, utilising high temperature (250 DegC)
seawater |
2020 |
0.5 |
Malaysia |
AIE
Engineering |
Petronas
Research |
Specialist
Corrosion Study |
|
150 |
DAR
Energy |
Petronas |
|
||||||
151 |
0.5 |
2H
Offshore |
|